Bradys Lane, Greendale - Carpark construction and footpath connection as part of Moorabool Shire Council’s (MSC) 2021-2022 Capital Works Program.
Works will be completed in two distinct stages.
Stage 1 (Civil) includes civil works to assist achieve improved walking pathways and parking areas; the works include construction of concrete footpath, drainage improvements, pram crossings, road realignment and pavement upgrade works. Stage 1 works are scheduled to start September and are planned to be completed in 8 weeks.
Stage 2 (Landscape) includes infill planting and landscaping works in the Bradys Ln carpark area. Stage 2 works will commence after completion of Stage 1 and are scheduled to be completed prior to 31 December 2021.
Work hours will generally be between 7:00am and 5:00pm, minor delays within these hours are to be expected. Vehicle access to properties and Egans Reserve may also be restricted during construction works. Contractor staff will notify residents in advance in relation to when this may occur.
Civil and landscaping drawings have been prepared by Council following community consultation in 2020. If you have any queries or concerns regarding design, please do not hesitate to contact Justin Horne – MSC Environment and Waste Education Manager on 03 5366 7100.